August 30, 2000

Birth of Japan's Largest Base Isolation Retrofit Work
Done "while the building is being used," without disturbing the tenants


Takenaka Corporation
Artist's impression of the completed Tokyo DIA Building base isolation work

Many examples of base isolation systems can be seen in newly constructed buildings around Japan, but there are only about 20 examples of base isolation improvement work (*1) being done on existing buildings, mostly on cultural assets and government buildings, but now more examples of this system being used on hospitals and research facilities can be seen.
Takenaka Corporation (President: Toichi Takenaka; Head Office: Osaka) is responsible for the improvement work (started in December, 1999 and due to be completed by November, 2001) being done on Buildings 1 through 4 of Mitsubishi Logistics Corporation's "Tokyo DIA Building," a complex housing a computer center and data storage facilities. This improvement work is not only the largest base isolation work ever undertaken in Japan, but it is also being done "while the building is being used" (*2), and is unique in that it will also incorporate some high-performance base isolation functions.


*1 Base isolation improvement work
Improvement work changing the building structure to a base isolation structure is done, by installing base isolation devices between the foundation of the building and the building itself, or between mid-level floors in a building so the energy of an earthquake doesn't affect the building directly. When this work is done in an existing building, it is called base isolation retrofit work.


*2 Base isolation procedure while the building is being used
Base isolation improvement work on a building can be done either after stopping use of the building, or while the building is being used. Base isolation improvement work on a building while the building is being used is an extremely effective method for strengthening and improving a building when the owner wants to increase the safety of the building during a major earthquake but the tenants cannot stop their day-to-day business.


Features of the "Base Isolation Work While the Building Is Being Used" in the Buildings 1 through 4 of the "Tokyo DIA Building"

1. The largest base isolation work ever undertaken in Japan, joining four buildings into one (see attachment 1)
With this work being done on Buildings 1 through 4, it is the first time that base isolation work is being tried joining a number of buildings, using 264 rubber bearings, 28 wall-type viscous dampers over an area of about 68,000m2. This work is not only the largest base isolation retrofit work, but also larger than any work ever done on a new building.


2. Base isolation work undertaken while computers inside the buildings were operating 24 hours a day
The "Tokyo DIA Building" houses many host computers and servers that continue to operate 24 hours a day. The base isolation work is being carried out on the foundations under the first basement floor "while the building is being used" without disturbing operations going on in the buildings. During the work, temporary strengthening is installed to give the building additional earthquake resistance. At the same time great care is taken not to affect the equipment and facilities housed inside the building.




3. High-performance base isolation functions
The response acceleration (gal) in the event of an earthquake the size of the Great Kanto Earthquake would be about 400gal in the underground foundation area, would increase the higher up the building you went, and on the 11th floor would be about twice as much, or about 800gal. In this project, the owner of the building has asked that the response acceleration be kept to under 200gal at the floor level of each floor, so high-performance type base isolation devices such as rubber bearings to limit the transmission of the earthquake motion to the building, and wall-type viscous dampers to reduce the earthquake energy have been used. As a result, it is possible to keep the shaking of the building to under 100gal.


Procedure of the "Base Isolation Work While the Building Is Being Used"

Buildings 1 through 4 of the "Tokyo DIA Building" complex are first joined together at their foundations, and the buildings are supported by the installation of braces and temporary supports. By doing so, the buildings are given more earthquake resistance during the work than beforehand, and then the piles are cut and the rubber bearings installed. 264 rubber bearings are installed, after which 28 wall-type viscous dampers are also installed, giving the entire complex high-performance base isolation.

  1. Struts are installed after earth-retaining walls are set up. Excavation work is carried out at the periphery of the building, and then under the building after retaining walls have been installed.

  2. Steel piles are pressed in, and mat slabs are installed.

  3. Temporary strengthening is installed to give the building additional earthquake-resistance while the work is being carried out.

  4. Temporary staging is installed to support the building, and the piles are then cut.

  5. Rubber bearings are installed into the cutout area of the piles, and fixed in place using concrete.

  6. Wall-type viscous dampers are installed.

  7. The struts and temporary strengthening are removed, and the base isolation work is complete.
At Takenaka, as well as being able to undertake base isolation work for new buildings, a large menu for base isolation work to be applied to existing buildings has also been developed. Takenaka can recommend the best method, including the best floor for installation of the base isolation system and the type of base isolation system, according to the location, size and use of a building.

Attachment 1





Attachment 2

Left: after base isolation work
Right: before base isolation work


It is said that computers don't malfunction if the response acceleration of earthquakes on the floor level on a given floor is below 200gal.



[Home Page]

Back

Copyright 2000, Takenaka Corporation